docs: adjust release management doc
Signed-off-by: Juergen Gross <jgross@suse.com> Acked-by: Wei Liu <wei.liu2@citrix.com>
This commit is contained in:
1 parent
f14e5a00bf
commit
2ec65db5ad
1 file changed
+18
-5
@@ -160,6 +160,11 @@ Contributors to gather a list of features for the release. Discuss the
|
||||
support status of new features with stakeholders. Help prepare the press
|
||||
release, write a blog post for the release.
|
||||
|
||||
Make sure the key people for doing the release (especially Community Manager,
|
||||
Release Manager and Release Technician) will be either available around the
|
||||
planned release date or have named a substitute being capable to perform the
|
||||
required tasks.
|
||||
|
||||
1. Collate a list of major changes: this should be done in collaboration
|
||||
between Release Manager, PR Personnel and key contributors. This should *not*
|
||||
be done on a public mailing list, to minimize the risk of release related
|
||||
@@ -198,12 +203,14 @@ releases typically done mid-week (Tuesday - Thursday).
|
||||
|
||||
4. Select the release date.
|
||||
|
||||
5. Check with relevant stake-holders (typically community manager) whether
|
||||
5. Specify the dates regarding support and security support in SUPPORT.md.
|
||||
|
||||
6. Check with relevant stake-holders (typically community manager) whether
|
||||
wiki documentation and PR is in good shape (for an example see
|
||||
https://wiki.xenproject.org/wiki/Category:Xen_4.9
|
||||
<https://wiki.xenproject.org/wiki/Category:Xen_4.9>)
|
||||
|
||||
6. Obtain a formal go-ahead from
|
||||
7. Obtain a formal go-ahead from
|
||||
|
||||
* the Community Manager
|
||||
* the Release Technician
|
||||
@@ -211,12 +218,12 @@ https://wiki.xenproject.org/wiki/Category:Xen_4.9
|
||||
Ask them to dry-run their checklist and confirm everything is OK. If not,
|
||||
arrange another RC and restart this checklist.
|
||||
|
||||
7. Do not commit to a release date until
|
||||
8. Do not commit to a release date until
|
||||
|
||||
* The exact xen.git commit id to be released is known.
|
||||
* That commit id has been satisfactorily tested.
|
||||
|
||||
8. Give PR Personnel final go-ahead, and instruct Release Technician to make
|
||||
9. Give PR Personnel final go-ahead, and instruct Release Technician to make
|
||||
release deliverables (tags and tarballs - will usually be in place the day
|
||||
before the release). At this point, PR collateral will be sent to reporters
|
||||
(typically 2-3 working days before the release date) and we cannot undo
|
||||
@@ -224,7 +231,7 @@ publications without questions being asked and risk of negative PR. It is
|
||||
acceptable to make a xen-devel@ announcement *before* the PR release date
|
||||
(blog, xen-announce@, press release).
|
||||
|
||||
9. Make the announcement on various mailing list, publish the blog post.
|
||||
10. Make the announcement on various mailing list, publish the blog post.
|
||||
|
||||
Allow for contingencies. It is not uncommon that some last minute (security or
|
||||
not) bugs are discovered. To provide a fix takes time, the test of the fix
|
||||
@@ -239,9 +246,15 @@ following things happen for the new Release Manager.
|
||||
|
||||
1. A JIRA (xenproject.atlassian.net) is created and proper permissions granted.
|
||||
2. Access to community test infrastructure is granted.
|
||||
In the common case the public pages at logs.test-lab.xenproject.org will
|
||||
suffice.
|
||||
3. Access to mailing list moderation panel is granted.
|
||||
4. An account for blog.xenproject.org is created.
|
||||
The account can be created by the new Release Manager, it might be necessary
|
||||
to adjust the access rights.
|
||||
5. An account for wiki.xenproject.org is created.
|
||||
The account can be created by the new Release Manager, it might be necessary
|
||||
to adjust the access rights.
|
||||
|
||||
# Email templates and scripts
|
||||
|
||||
|
||||